Free calculator · Workshops & manufacturing

How many hours do you really have this week?

Hours on paper are not the hours you have. Take off efficiency and stoppages, set them against the work to do and see whether the week holds.

Those working side by side on the same kind of work.
The time actually spent producing, after set-ups, waiting and small hitches. If you do not know it, start from 75–85%.
Total hours, all machines together.
Processing hours of the jobs due, set-ups included.

Available hours per week

122 h

out of 160 h in theory

At the limit2 h of slack left: one stoppage or rush job and something slips.
Theoretical hoursmachines × hours × shifts × days
160 h
Lost to efficiency and stoppages24% of the theoretical hours
38 h
Utilisation120 h of work over 122 h available
98%
Slackin the week
+2 h
Available hours per monthon average: 52 weeks divided by 12
529 h

The example is already filled in: change the figures and the result updates. The sum runs in your browser: nothing is sent or saved.

How it is worked out

Three steps, with the example’s figures.

Theoretical hours

Machines × hours per shift × shifts × days. In the example: 4 × 8 × 1 × 5 = 160 hours.

Available hours

Theoretical hours times real efficiency, minus planned stoppages: 160 × 80% − 6 = 122 hours. These are the hours you can promise against.

Utilisation

Work to do divided by available hours: 120 ÷ 122 = 98%. Above 85% one surprise is enough for something to slip; above 100% the hours are not enough.

With Taktra

In Taktra this sum redoes itself, every day.

Scheduling shows the load machine by machine and utilisation for the next two weeks, with the people present, public holidays, stoppages and maintenance. When something changes, dates are recalculated.

  • Load and utilisation per machine, day by day
  • An open stoppage zeroes capacity until the restart
  • Expected date of every job from real capacity
Taktra scheduling: operations day by day and machine utilisation over the next two weeks

Questions

Before you trust a number.

What is the difference between theoretical and available capacity?

Theoretical capacity counts every hour the machines could work. Available capacity takes off what really happens: set-ups, waiting, breaks, stoppages and maintenance. Promise dates to customers on the available figure.

How do I estimate real efficiency if I do not measure it?

Take a typical week: hours produced (pieces × standard time) divided by the hours staffed on the machines. Without data, 75–85% is a prudent starting point; below 70% a lot usually goes on set-ups and waiting.

What is a sensible utilisation?

Between 70% and 85% the floor runs full but can absorb a rush job or a stoppage. Above 85% every surprise moves a delivery; above 100% you need overtime or different dates.

Give your work
its shape.